France

Construction site in the middle of the city of Paris

LCS winches and crane units in action for a construction site in the middle of the city of Paris.

  • LCS supplied two electro-hydraulic winches, two crane units with a payload of 20 to and various components for the removal of construction material. Mecamont Hydro installed two independent systems with two transport boxes each, which transported the excavated material to a ship on the Seine. The construction site in the middle of the city was located next to an apartment building, resulting in operating hours from Monday to Friday from 08:00 to 18:00. As the construction site was difficult to access by truck due to heavy traffic, cable crane systems were installed, which were driven by electro-hydraulic winches to keep the noise level as low as possible.

Customer

Mecamont Hydro SAS

Project owner

n/a

Location

France

Year

2019

Technical project data (winch)

Drive

electro-hydraulic

Power

250 kW

Max. tensile force

130 kN

Max. rope speed

5 m/s

Rope capacity

Ø 24 mm, 1,250 m

Weight

7,800 kg

Technical project data (crane unit)

Drive

diesel-hydraulic

Power

73 kW

Payload

20 to

Max. lifting height

60 m

Max. lifting speed

0.75 m/s

Rope capacity

Ø 12 mm, 260 m